NASA Systems Engineering Workspace

This is the authoritative systems engineering documentation package for the UA NASA Robotics Lunabotics team. It adapts the NASA Systems Engineering Handbook life-cycle structure to the Lunabotics competition calendar. The NASA handbook and Lunabotics guidebook source files stay at the root. Traceability references and phase-specific source maps live in context/. Phase entry and exit checks live in Checklists/. Controlled templates live in Phase Deliverables/. Filled examples live in Phase Deliverables Examples/.

All team members SHALL use the checklists and templates in this repo as the governing documents for their phase work. Changes to baselines must follow the configuration control rules documented in the active SEMP.

School-year roadmap

Use this as the at-a-glance plan for an August to early May academic year. It assumes Pre-A through Phase B are closed before winter break so spring can be used for build, integration, readiness, and operations. The month-by-month version with activity details, gate criteria, and competition submission deadlines lives in context/school_year_se_timeline.md.

Note on dates: The Gantt chart below is projected for the 2026-2027 academic year and the corresponding Lunabotics competition season. Confirm actual competition event dates and submission deadlines against the current Lunabotics Guidebook when it is released each year. The source file in this repo (draft-lunabotics-word-clean-versions-no-formatting-9-5-25.md) covers the 2025-2026 season and is retained as the source of structural and scoring guidance until the 2026-2027 guidebook is available.

gantt
	title Student Systems Engineering Roadmap
	dateFormat  YYYY-MM-DD
	axisFormat  %b

	section Fall
	Pre-A and MCR                :prea, 2026-08-17, 2026-09-18
	Phase A and SRR or MDR or SDR:pha, 2026-09-21, 2026-10-16
	Phase B and PDR              :phb, 2026-10-19, 2026-12-04

	section Spring
	Phase C with CDR and SIR     :phc, 2027-01-11, 2027-02-19
	Phase D with TRR ORR FRR/MRR :phd, 2027-02-22, 2027-04-16
	Phase E operations           :phe, 2027-04-19, 2027-05-07
	Phase F closeout overlap     :phf, 2027-04-26, 2027-05-07

	section Gates
	MCR                          :milestone, mcr, 2026-09-04, 1d
	SRR or MDR or SDR            :milestone, srr, 2026-10-16, 1d
	PDR                          :milestone, pdr, 2026-12-04, 1d
	CDR and SIR                  :milestone, cdr, 2027-02-19, 1d
	TRR                          :milestone, trr, 2027-03-05, 1d
	ORR                          :milestone, orr, 2027-03-26, 1d
	FRR or MRR                   :milestone, frr, 2027-04-16, 1d
	Ops complete and DRR-ready   :milestone, drr, 2027-05-07, 1d

	section Deliverables
	Project Management Plan Due                :milestone, pmp, 2026-09-29, 1d
	Statement of Support – Institution         :milestone, support_inst, 2026-09-29, 1d
	Statement of Support – Faculty             :milestone, support_fac, 2026-09-29, 1d
	Statement of Rights of Use                 :milestone, rights_use, 2026-09-29, 1d
	Preliminary Design Review Report Due       :milestone, pdr_report, 2026-11-20, 1d
	Team Selections Announced                  :milestone, team_select, 2026-12-14, 1d
	Student and Faculty Registration Due       :milestone, reg, 2027-01-15, 1d
	NASA Media Release Due                     :milestone, media_release, 2027-01-15, 1d
	KSC Waste Management Overview Due          :milestone, waste_overview, 2027-01-15, 1d
	Systems Engineering Paper Due              :milestone, se_paper, 2027-04-08, 1d
	Robot Data Report Due                      :milestone, robot_data, 2027-04-29, 1d
	Proof of Life Review Due                   :milestone, proof_life, 2027-04-29, 1d
	Practice Runs at KSC                       :milestone, practice_runs, 2027-05-20, 2d
Loading

IPT ownership handoff

Use this to show when the team stops treating subsystem leads as provisional contributors and starts treating them as formal owners. Systems and PM keep baseline control the whole year, but the main handoff to IPT-led execution happens at the Phase A gate on entry to Phase B.

gantt
	title IPT Ownership Handoff Across the School Year
	dateFormat  YYYY-MM-DD
	axisFormat  %b

	section Systems and PM
	Whole-team concept leadership        :spm1, 2026-08-17, 2026-09-04
	Baseline control and integration     :spm2, 2026-09-07, 2027-05-07

	section Mobility and Structures
	Provisional lead and concept support :mob1, 2026-08-17, 2026-10-16
	Formal subsystem ownership           :mob2, 2026-10-19, 2027-05-07

	section Excavation and Material Handling
	Provisional lead and concept support :exc1, 2026-08-17, 2026-10-16
	Formal subsystem ownership           :exc2, 2026-10-19, 2027-05-07

	section Electrical and Avionics
	Provisional lead and concept support :ele1, 2026-08-17, 2026-10-16
	Formal subsystem ownership           :ele2, 2026-10-19, 2027-05-07

	section Autonomy and Controls
	Provisional lead and concept support :aut1, 2026-08-17, 2026-10-16
	Formal subsystem ownership           :aut2, 2026-10-19, 2027-05-07

	section Test Operations and Safety
	Shared readiness planning            :tos1, 2026-08-17, 2026-10-16
	Formal field and verification owner  :tos2, 2026-10-19, 2027-05-07
Loading

Compact phase index

Phase Intent Checklist Context Templates Examples Main review
Pre-A Feasible concepts and concept selection Phase Pre-A Pre-A source map Pre-A package Pre-A examples MCR
Phase A Baselined ConOps, architecture, and top-level requirements Phase A Phase A source map Phase A package Phase A examples SRR, MDR or SDR
Phase B Preliminary design and technology completion Phase B Phase B source map Phase B package Phase B examples PDR
Phase C Detailed design, fabrication, and integration entry readiness Phase C Phase C source map Phase C package Phase C examples CDR, PRR if needed, SIR
Phase D Assembly, integration, verification, validation, and field readiness Phase D Phase D source map Phase D package Phase D examples TRR, SAR, ORR, FRR or MRR
Phase E Operations, sustainment, and bounded in-season evolution Phase E Phase E source map Phase E package Phase E examples PLAR-style assessment, CERR-style readiness, system upgrade review, safety review
Phase F Closeout, archive, disposition, and cohort handoff Phase F Phase F source map Phase F package Phase F examples DRR

Folder structure and contents

Root source

Checklists

Context

Pre-A deliverables

Phase A deliverables

Phase B deliverables

Phase C deliverables

Phase D deliverables

Phase E deliverables

Phase F deliverables